The project started and your immediate supervisor asked for a field report on day 10. The field report you submitted on day 10 is given below.Field Report at Day 10ActivityActual Completion %Cost IncurredA1002400B1001200C1004000D804000E254000F00Question 3. Calculate the BCWP, BCWS, CPI, SPI, CV, and SV for the field report day 10. Show your calculations, and summarize the results on a table.