Use the information contained below to compress one time unit per move using the least cost method.

Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed the adjusted total cost.
Crash Cost (Slope) TTTI Act. Maximum Crash Time Normal Time Normal Cost 1 A 100 2 150 1 80 3 100 C 60 1 200 1 D 40 5 200 F 40 5 200 40 7 150 20 G 1 5 200 1 H 200 C 2 3 Project duration 16 3 D G A 1x 5 2 Total direct cost 1.400 F 5